jain.com

January 2024 debt repayment

Company: TeraWulf

Subject kind
financing
Statement date
2024-01-02
Promised by
2024-01-31
Promised amount
11000000.0 USD
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

P6 reports $21.4 million of repayments tied to 2023 excess cash flow sweeps and an $18.6 million prepayment in February 2024. No passage confirms an $11 million repayment in January 2024.

“Following significant debt repayments totaling $21.4 million related to 2023 quarterly excess cash flow sweep payments and an $18.6 million voluntary prepayment in February 2024”
2024-03-05 · terawulf 8-K exhibit (wulf23resultsand24outloo.htm) View cached copy (2026-11-09)Live source ↗

Checked November 15, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf expects to make an $11 million debt repayment in January 2024, reducing future interest payments.

Source (primary)

terawulf 8-K exhibit (wulfdec23opsreport01-03x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-15)Live source ↗

Quote: “with an $11 million expected repayment in January 2024, thereby reducing the Company's future interest payments”

How we checked this

Checked on November 16, 2026. The cited source supports every part of this claim.

The release states an $11 million repayment is expected in January 2024, thereby reducing future interest payments.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000007/wulfdec23opsreport01-03x.htm) in full (11,186 characters, retrieved November 15, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (wulfdec23opsreport01-03x.htm)

Quote: “with an $11 million expected repayment in January 2024, thereby reducing the Company's future interest payments”

View cached copy (2026-11-15)Live source ↗

Record of changes

November 15, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 15, 2026 — outcome unconfirmed