Kentucky Power files with KY PSC for TeraWulf agreement and Muskie infrastructure

Company: TeraWulf

Subject kind
regulatory
Statement date
2026-11-13
Promised by
2027-06-30
Promised amount
760.0 MW
Current status
stated

The claim, verbatim

Kentucky Power filed with the Kentucky PSC seeking approval of the amended TeraWulf agreement, a 760-MW gas facility and a new substation to serve Muskie; decisions could come as early as mid-2027.

Source (primary)

Kentucky Power Files for Gas Plant and Substation to Serve TeraWulf - Securities.io (-, news_article)
View cached copy (2026-11-14)Live source ↗Archive.org ↗

Quote: “Kentucky Power said decisions on the filings could come as early as mid-year 2027, subject to the commission's review schedule.”

How we checked this

Checked on November 15, 2026. The cited source supports every part of this claim.

The article reports the PSC filings covering the amended agreement, the 760-MW gas plant and the new substation, and says decisions could come as early as mid-year 2027.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.securities.io/kentucky-power-files-for-gas-plant-and-substation-to-serve-terawulf/) in full (10,816 characters, retrieved November 14, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Kentucky Power Files for Gas Plant and Substation to Serve TeraWulf - Securities.io

Quote: “Kentucky Power said decisions on the filings could come as early as mid-year 2027, subject to the commission's review schedule.”

View cached copy (2026-11-14)Live source ↗Archive.org ↗