Expansion to 10 EH/s in H1 2024
Company: IREN
What the later record shows
Delivered on time · happened May 14, 2024
On May 14, 2024 IREN reported that operating hashrate had reached 10 EH/s ahead of schedule, before the H1 2024 deadline.
“Operating hashrate currently 10 EH/s, milestone achieved ahead of schedule”
2024-05-14 · iren 8-K exhibit (ef20027345_ex99-5.htm) View cached copy (2026-11-05)Live source ↗
Checked November 12, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN is expanding operating capacity to 10 EH/s in H1 2024; Childress Phase 1 (the expansion to 10 EH/s) is on track for H1 2024.
Source (primary)
iren 8-K exhibit (ef20020920_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-12)Live source ↗
Quote: “H1 2024 – expansion to 10 EH/s ongoing ... Phase 1 (expansion to 10 EH/s) – on track for H1 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20020920_ex99-1.htm)
Quote: “H1 2024 – expansion to 10 EH/s ongoing ... Phase 1 (expansion to 10 EH/s) – on track for H1 2024”
confirms iren 8-K exhibit (ef20027345_ex99-5.htm)
Quote: “Operating hashrate currently 10 EH/s, milestone achieved ahead of schedule”