Delivery and commissioning of additional 568 GPUs in Q2 2024
Company: IREN
What the later record shows
Delivered on time · happened June 5, 2024
The June 5, 2024 update reports 816 H100 GPUs operating, so the additional 568 GPUs were delivered and commissioned during Q2 2024.
“AI Cloud Services • 816 NVIDIA H100 GPUs operating o 504 GPUs contracted with Poolside”
2024-06-05 · iren 8-K exhibit (ef20030723_ex99-1.htm) View cached copy (2026-11-04)Live source ↗
“As of July 31, 2024, our GPU fleet comprises 816 NVIDIA H100 GPUs, which have serviced multiple customers.”
2024-08-27 · IREN 20-F filed 2024-08-28 View cached copy (2026-08-31)Live source ↗
Checked November 11, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Iris Energy expects delivery and commissioning of the additional 568 H100 GPUs during Q2 2024.
Source (primary)
iren 8-K exhibit (ef20021677_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-11)Live source ↗
Quote: “Delivery and commissioning of the additional GPUs is expected during Q2 2024.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (ef20021677_ex99-1.htm)
Quote: “Delivery and commissioning of the additional GPUs is expected during Q2 2024.”
confirms IREN 20-F filed 2024-08-28
Quote: “As of July 31, 2024, our GPU fleet comprises 816 NVIDIA H100 GPUs, which have serviced multiple customers.”
confirms iren 8-K exhibit (ef20030723_ex99-1.htm)
Quote: “AI Cloud Services • 816 NVIDIA H100 GPUs operating o 504 GPUs contracted with Poolside”