jain.com

Exaion demand for 30+ MW compute by end-2027

Company: Marathon Digital

Subject kind
guidance
Statement date
2026-11-08
Promised by
2027-12-31
Promised amount
30.0 MW
Current status
stated

The claim, verbatim

Exaion customers and prospects have expressed demand for more than 30 MW of compute capacity for delivery by the end of 2027.

Source (primary)

marathon-digital 8-K exhibit (q326shareholderletter.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-10)Live source ↗

Quote: “Exaion's customers and prospects have expressed demand for more than 30 MW of compute capacity for delivery by the end of 2027.”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The letter directly states the more than 30 MW of expressed demand and the end-2027 delivery timing.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1507605/000150760526000026/q326shareholderletter.htm) in full (43,591 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms marathon-digital 8-K exhibit (q326shareholderletter.htm)

Quote: “Exaion's customers and prospects have expressed demand for more than 30 MW of compute capacity for delivery by the end of 2027.”

View cached copy (2026-11-10)Live source ↗