jain.com

Portfolio expected to exceed 4 GW

Company: Marathon Digital

Subject kind
facility capacity
Statement date
2026-11-08
Promised amount
4000.0 MW
Current status
stated

The claim, verbatim

MARA owns and operates approximately 1 GW and expects its portfolio to reach over 4 GW subject to Long Ridge closing and Matagorda energization.

Source (primary)

marathon-digital 8-K exhibit (q326shareholderletter.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-10)Live source ↗

Quote: “Subject to the closing of Long Ridge and energization of Matagorda, we expect that portfolio to reach over 4 GW.”

How we checked this

Checked on November 11, 2026. The cited source supports every part of this claim.

The letter states the approximately 1 GW owned and operated, the over 4 GW expectation and both stated conditions.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1507605/000150760526000026/q326shareholderletter.htm) in full (43,591 characters, retrieved November 10, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms marathon-digital 8-K exhibit (q326shareholderletter.htm)

Quote: “Subject to the closing of Long Ridge and energization of Matagorda, we expect that portfolio to reach over 4 GW.”

View cached copy (2026-11-10)Live source ↗