550 MW deployed infrastructure in 2025
Company: TeraWulf
What the later record shows
The date slipped
The May 2025 plan targets 225 MW for bitcoin mining plus about 60 MW net of HPC hosting in 2025, well short of 550 MW. No passage shows 550 MW deployed in 2025.
“225 MW to be deployed for bitcoin mining in 2025”
2025-05-08 · Investor Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
“72.5 (gross) / 60 (net) MW contracted and expected online in 2025”
2025-05-08 · Investor Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked November 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf targets 550 MW of deployed infrastructure in 2025, or about 28.3 EH/s with current-generation miners.
Source (primary)
terawulf 8-K exhibit (wulf23resultsand24outloo.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-09)Live source ↗
Quote: “reaching 550 MW, or approximately 28.3 EH/s with current generation of miners, of deployed infrastructure in 2025”
How we checked this
Checked on November 10, 2026. The cited source supports every part of this claim.
The press release gives both the 550 MW target for 2025 and the 28.3 EH/s equivalent.
Confirmed in the source:
- TeraWulf targets 550 MW of deployed infrastructure in 2025
- 550 MW equates to approximately 28.3 EH/s with current-generation miners
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000053/wulf23resultsand24outloo.htm) in full (18,117 characters, retrieved November 9, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (wulf23resultsand24outloo.htm)
Quote: “reaching 550 MW, or approximately 28.3 EH/s with current generation of miners, of deployed infrastructure in 2025”
delays Investor Presentation
Quote: “225 MW to be deployed for bitcoin mining in 2025”