jain.com

300 MW infrastructure capacity by year-end 2024

Company: TeraWulf

This claim was marked delayed on November 9, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2024-03-05
Promised by
2024-12-31
Promised amount
300.0 MW
Current status
delayed

What the later record shows

The date slipped · new target March 31, 2025

In May 2024 the company moved the ~300 MW target to Q1 2025. After the Nautilus sale it reported 225 MW in operation in Q1 2025, so 300 MW was not reached by year-end 2024.

“bringing TeraWulf’s total operational capacity to approximately 300 MW by the first quarter of 2025”
2024-05-12 · terawulf 8-K exhibit (aex991xearningsreleasexq12.htm) View cached copy (2026-11-06)Live source ↗
“225 MW in operation Q1 2025 ➢ 50 MW (MB-5) expansion online April 2025”
2025-05-08 · Investor Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked November 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf reiterated its commitment to reach 300 MW of infrastructure capacity in operation by the close of 2024.

Source (primary)

terawulf 8-K exhibit (wulf23resultsand24outloo.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-09)Live source ↗

Quote: “the Company reiterates its commitment to achieving 300 MW of infrastructure capacity in operation by the close of 2024”

How we checked this

Checked on November 10, 2026. The cited source supports every part of this claim.

The press release states this commitment directly.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000053/wulf23resultsand24outloo.htm) in full (18,117 characters, retrieved November 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (wulf23resultsand24outloo.htm)

Quote: “the Company reiterates its commitment to achieving 300 MW of infrastructure capacity in operation by the close of 2024”

View cached copy (2026-11-09)Live source ↗

delays Investor Presentation

Quote: “225 MW in operation Q1 2025 ➢ 50 MW (MB-5) expansion online April 2025”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

delays terawulf 8-K exhibit (aex991xearningsreleasexq12.htm)

Quote: “bringing TeraWulf’s total operational capacity to approximately 300 MW by the first quarter of 2025”

View cached copy (2026-11-06)Live source ↗

Record of changes

November 9, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 9, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.