Mining portfolio to reach ~1.1 GW, 54% self-owned

Company: Marathon Digital

Subject kind
facility capacity
Statement date
2024-03-17
Promised by
2024-12-31
Promised amount
1100.0 MW
Current status
verified

What the later record shows

Delivered on time

The May 8, 2024 release states the portfolio reached more than 1.1 GW, with 54% on directly owned and operated sites, before the end-2024 deadline.

“Closed multiple acquisitions of data centers, increasing mining portfolio to more than 1.1 gigawatts of capacity, 54% of which resides on sites now directly owned and operated by the Company”
2024-05-08 · marathon-digital 8-K exhibit (ex99-1.htm) View cached copy (2026-11-06)Live source ↗

Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

After the acquisition closes and the site is expanded in 2024, Marathon's Bitcoin mining portfolio will be about 1.1 GW across eleven sites on three continents, with 54% on sites it directly owns and operates.

Source (primary)

marathon-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗

Quote: “Following the close of this acquisition and the anticipated expansion of the site in 2024, Marathon will have increased the number of megawatts in its mining portfolio to 1.1 gigawatts, 54% of which will reside on sites directly owned and operated by the Company.”

How we checked this

Checked on November 9, 2026. The cited source supports every part of this claim.

The release gives the roughly 1.1 GW total and the 54% self-owned share, and the CEO quote adds that the portfolio will span eleven sites on three continents.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1507605/000149315224010217/ex99-1.htm) in full (8,120 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms marathon-digital 8-K exhibit (ex99-1.htm)

Quote: “Following the close of this acquisition and the anticipated expansion of the site in 2024, Marathon will have increased the number of megawatts in its mining portfolio to 1.1 gigawatts, 54% of which will reside on sites directly owned and operated by the Company.”

View cached copy (2026-11-08)Live source ↗

confirms marathon-digital 8-K exhibit (ex99-1.htm)

Quote: “Closed multiple acquisitions of data centers, increasing mining portfolio to more than 1.1 gigawatts of capacity, 54% of which resides on sites now directly owned and operated by the Company”

View cached copy (2026-11-06)Live source ↗

Record of changes

November 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 8, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.