550 MW (~28.3 EH/s) deployed by end of 2025

Company: TeraWulf

This claim was marked delayed on November 8, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2024-03-18
Promised by
2025-12-31
Promised amount
550.0 MW
Current status
delayed

What the later record shows

The date slipped

As of June 30, 2026, TeraWulf had 145 MW of bitcoin mining capacity energized, with miner buildings being repurposed for HPC. That is far below 550 MW / ~28.3 EH/s by end of 2025.

“has energized 145 MW of capacity across three buildings and supporting infrastructure at the site”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗
“During the six months ended June 30, 2026, two miner buildings were repurposed or placed out of service to support the HPC development”
2026-08-04 · TeraWulf 10-Q filed 2026-08-05 View cached copy (2026-08-31)Live source ↗

Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf plans to scale to 550 MW, equivalent to approximately 28.3 EH/s with current-generation miners, by the end of 2025.

Source (primary)

terawulf 8-K exhibit (exhibit991-earningsrelea.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗

Quote: “it endeavors to deploy 550 MW, equivalent to approximately 28.3 EH/s, utilizing the current generation of miners by 2025”

How we checked this

Checked on November 9, 2026. The cited source supports every part of this claim.

The release says the company endeavors to deploy 550 MW (about 28.3 EH/s with current-generation miners) by 2025, and the CEO is quoted saying the scale-up to 550 MW is planned by the conclusion of 2025.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000066/exhibit991-earningsrelea.htm) in full (27,213 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (exhibit991-earningsrelea.htm)

Quote: “it endeavors to deploy 550 MW, equivalent to approximately 28.3 EH/s, utilizing the current generation of miners by 2025”

View cached copy (2026-11-08)Live source ↗

delays TeraWulf 10-Q filed 2026-08-05

Quote: “has energized 145 MW of capacity across three buildings and supporting infrastructure at the site”

View cached copy (2026-08-31)Live source ↗

Record of changes

November 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 8, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.