300 MW operational capacity by end of 2024

Company: TeraWulf

This claim was marked delayed on November 8, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2024-03-18
Promised by
2024-12-31
Promised amount
300.0 MW
Current status
delayed

What the later record shows

The date slipped · new target March 31, 2025

In May 2024 the company moved the ~300 MW target to Q1 2025. The Nautilus stake was sold in October 2024, and Q1 2025 operations were 225 MW, so 300 MW was not reached by end-2024.

“bringing TeraWulf’s total operational capacity to approximately 300 MW by the first quarter of 2025”
2024-05-12 · terawulf 8-K exhibit (aex991xearningsreleasexq12.htm) View cached copy (2026-11-06)Live source ↗
“On October 2, 2024, WULF sold 25% equity interest in Nautilus to Talen Energy”
2024-11-11 · terawulf 8-K exhibit (wulfq32024investorpres11.htm) View cached copy (2026-10-25)Live source ↗

Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

TeraWulf reaffirmed its commitment to reach operational infrastructure capacity of 300 MW by the end of 2024.

Source (primary)

terawulf 8-K exhibit (exhibit991-earningsrelea.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗

Quote: “the Company reaffirms its commitment to achieving an operational infrastructure capacity of 300 MW by the end of 2024”

How we checked this

Checked on November 9, 2026. The cited source supports every part of this claim.

The release states that the company reaffirms its commitment to 300 MW of operational infrastructure capacity by the end of 2024.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330124000066/exhibit991-earningsrelea.htm) in full (27,213 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (exhibit991-earningsrelea.htm)

Quote: “the Company reaffirms its commitment to achieving an operational infrastructure capacity of 300 MW by the end of 2024”

View cached copy (2026-11-08)Live source ↗

delays terawulf 8-K exhibit (wulfq32024investorpres11.htm)

Quote: “On October 2, 2024, WULF sold 25% equity interest in Nautilus to Talen Energy”

View cached copy (2026-10-25)Live source ↗

delays terawulf 8-K exhibit (aex991xearningsreleasexq12.htm)

Quote: “bringing TeraWulf’s total operational capacity to approximately 300 MW by the first quarter of 2025”

View cached copy (2026-11-06)Live source ↗

Record of changes

November 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 8, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.