12 EH/s additional miners installed within 9 months

Company: IREN

Subject kind
facility timeline
Statement date
2024-03-31
Promised by
2024-12-31
Current status
verified

What the later record shows

Delivered on time · happened September 30, 2024

Hashrate grew from 8 EH/s to 21 EH/s operating by the September 2024 update, which exceeds the 12 EH/s addition within the nine-month window. It reached 31 EH/s by year-end.

“Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”
2024-10-03 · iren 8-K exhibit (irensepmonthlyupdate4oct.htm) View cached copy (2026-10-26)Live source ↗
“31 EH/s year-end target achieved (original target of 20 EH/s), highlight video here”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗

Checked November 8, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN plans to progressively ship and install 12 EH/s of additional mining capacity over the next 9 months.

Source (primary)

iren 8-K exhibit (ef20025647_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-08)Live source ↗

Quote: “12 EH/s additional capacity to be progressively shipped and installed during the next 9 months”

How we checked this

Checked on November 9, 2026. The cited source supports every part of this claim.

The April 1, 2024 update states that 12 EH/s of additional capacity is to be progressively shipped and installed during the next 9 months. A footnote adds that 9 EH/s of this depends on purchase options not yet exercised.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1878848/000114036124016752/ef20025647_ex99-1.htm) in full (14,965 characters, retrieved November 8, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms iren 8-K exhibit (ef20025647_ex99-1.htm)

Quote: “12 EH/s additional capacity to be progressively shipped and installed during the next 9 months”

View cached copy (2026-11-08)Live source ↗

confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)

Quote: “31 EH/s year-end target achieved (original target of 20 EH/s), highlight video here”

View cached copy (2026-10-21)Live source ↗

confirms iren 8-K exhibit (irensepmonthlyupdate4oct.htm)

Quote: “Childress (Texas, USA) 200 11.1 Complete Operating Total Operating 360 21”

View cached copy (2026-10-26)Live source ↗

Record of changes

November 8, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 8, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.