Contracted and operating capacity

Company: TeraWulf

Subject kind
facility capacity
Statement date
2026-11-05
Promised amount
839.0 MW
Current status
stated

The claim, verbatim

TeraWulf has 839 MW of contracted critical IT, made up of 102 MW operating and 737 MW under construction, representing about $27B of contracted revenue.

Source (primary)

terawulf 8-K exhibit (terawulfq32026investorpr.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-07)Live source ↗

Quote: “839 MW contracted = 102 MW operating + 737 MW under construction”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (terawulfq32026investorpr.htm)

Quote: “839 MW contracted = 102 MW operating + 737 MW under construction”

View cached copy (2026-11-07)Live source ↗