Core42 HPC capacity delivery in 2025
Company: TeraWulf
What the later record shows
Partly delivered · new target March 31, 2026
Only 18 of the 60 critical IT MW were in place at year-end 2025. By February 2026, 39 MW had been delivered (Wulf Den, CB-1 and CB-2A), with the last 21 MW expected in Q1 2026.
“Wulf Den & CB-1 delivered (18 MW) ➢ CB-2A delivered (21 MW) ➢ CB-2B: 21 MW expected to be delivered in Q1”
2026-02-26 · Q4 Earnings Update Presentation View cached copy (2026-10-13)Live source ↗Archive.org ↗
“pursuant to which we committed to deliver 60 MW of critical IT load”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“As of December 31, 2025 the Lake Mariner Data Campus operated 245 MW of legacy bitcoin mining capacity and had 18 critical IT MW of HPC capacity.”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf says it is on track to deliver 60 MW of critical HPC hosting capacity to Core42 in 2025.
Source (primary)
Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “On track to deliver 60 MW of critical HPC hosting capacity to Core42 in 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Investor Presentation
Quote: “On track to deliver 60 MW of critical HPC hosting capacity to Core42 in 2025”