Core42 leased capacity in 2025
Company: TeraWulf
What the later record shows
Delivered late · happened March 31, 2026
Only 18 critical IT MW was energized at the end of 2025, with the remaining leases expected to commence in 2026. All Core42 leases had commenced by March 31, 2026, but at 60 critical IT MW; no passage reconciles this with the claimed 72.5 MW, which may be a gross figure.
“Certain of the Core42 HPC Leases commenced in 2025 and the remainder of the HPC Leases are expected to commence in 2026.”
2026-02-26 · TeraWulf 10-K filed 2026-02-27 View cached copy (2026-08-31)Live source ↗
“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“All of the Core42 Leases have commenced which comprised 60 critical IT MW HPC lease capacity as of March 31, 2026.”
2026-05-07 · TeraWulf 10-Q filed 2026-05-08 View cached copy (2026-08-31)Live source ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Leased capacity includes 72.5 MW for Core42 in 2025.
Source (primary)
WULF Expands Fluidstack Deal (IR page (investors.terawulf.com), ir_release)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “Core42: 72.5 MW in 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms WULF Expands Fluidstack Deal
Quote: “Core42: 72.5 MW in 2025”
confirms TeraWulf 10-K filed 2026-02-27
Quote: “Certain of the Core42 HPC Leases commenced in 2025 and the remainder of the HPC Leases are expected to commence in 2026.”
confirms TeraWulf 10-Q filed 2026-05-08
Quote: “All of the Core42 Leases have commenced which comprised 60 critical IT MW HPC lease capacity as of March 31, 2026.”
confirms View 10-K PDF
Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity and remains on track to deliver additional contracted capacity”