jain.com

Capex per MW

Company: TeraWulf

Subject kind
guidance
Statement date
2025-11-10
Promised amount
8000000.0 USD/MW
Current status
stated

The claim, verbatim

Capex is estimated at $8-10 million per MW of critical IT load, underlying $1.3B-$1.7B of Abernathy uses (low end recorded).

Source (primary)

Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗

Quote: “Capex of $8MM - $10MM per MW of critical IT load”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Investor Presentation

Quote: “Capex of $8MM - $10MM per MW of critical IT load”

View cached copy (2026-11-06)Live source ↗Archive.org ↗