Contracted capacity outlook through 2028
Company: TeraWulf
The claim, verbatim
Chart of capacity under contract shows ~1,350-2,100 MW critical IT by 2028, assuming incremental signings of 250-500 MW annually and subject to customer demand and regulatory approvals (low end recorded).
Source (primary)
Investor Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “Future deployment figures assume an incremental average of 250-500 MW annually and are subject to customer demand and regulatory approvals for power draw beyond existing interconnection agreements.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Investor Presentation
Quote: “Future deployment figures assume an incremental average of 250-500 MW annually and are subject to customer demand and regulatory approvals for power draw beyond existing interconnection agreements.”