Chesapeake Data campus plan
Company: TeraWulf
The claim, verbatim
The Morgantown, Maryland campus is planned as a net generator with 1 GW of on-site generation, 1 GW of data center load, and 500 MW of battery storage across two equal phases.
Source (primary)
Q1 2026 Earnings Update Presentation (IR page (investors.terawulf.com), ir_presentation)
View cached copy (2026-11-06)Live source ↗Archive.org ↗
Quote: “1 GW 1 GW 500 MW ON-SITE GENERATION DATA CENTER LOAD BATTERY STORAGE”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Q1 2026 Earnings Update Presentation
Quote: “1 GW 1 GW 500 MW ON-SITE GENERATION DATA CENTER LOAD BATTERY STORAGE”