295 MW operational by YE 2024
Company: TeraWulf
What the later record shows
The date slipped
The track-record chart indicates 195 MW in 4Q 2024 and 225 MW in Q1 2025, with the 50 MW MB-5 expansion not online until April 2025. That means 295 MW was not operational by year-end 2024, and no passage gives a new date for that figure.
“225 MW in operation Q1 2025 ➢ 50 MW (MB-5) expansion online April 2025”
2025-05-08 · Investor Presentation View cached copy (2026-11-05)Live source ↗Archive.org ↗
“195 MW 195 MW 30 MW 110 MW 60 MW 60 MW 0.3 EH/s 3 MW 1H 2022 2H 2022 1H 2023 2H 2023 3Q 2024 4Q 2024 1Q 2025”
2025-05-08 · Investor Presentation View cached copy (2026-11-05)Live source ↗Archive.org ↗
Checked November 6, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf targets 295 MW of operational capacity by year-end 2024.
Source (primary)
terawulf 8-K exhibit (wulfinvestorpresentation.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-06)Live source ↗
Quote: “Target 295 MW operational by YE 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfinvestorpresentation.htm)
Quote: “Target 295 MW operational by YE 2024”
delays Investor Presentation
Quote: “225 MW in operation Q1 2025 ➢ 50 MW (MB-5) expansion online April 2025”