jain.com

Contracted portfolio full deployment

Company: Riot

Subject kind
facility capacity
Statement date
2026-11-03
Promised by
2028-07-31
Promised amount
1151.0 MW
Current status
stated

The claim, verbatim

The 1,151 IT MW of contracted leases across AMD, Rockdale and Corsicana is expected to reach full capacity delivery by July 2028.

Source (primary)

riot 8-K exhibit (riot-ex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-05)Live source ↗

Quote: “Full Deployment4 May 2027 June 2028 July 2028 July 2028”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms riot 8-K exhibit (riot-ex99d2.htm)

Quote: “Full Deployment4 May 2027 June 2028 July 2028 July 2028”

View cached copy (2026-11-05)Live source ↗