16 MW Austin HPC capacity delivered early for CoreWeave

Company: Core Scientific

Subject kind
facility capacity
Statement date
2024-06-03
Promised amount
16.0 MW
Current status
stated

The claim, verbatim

Under a March 2024 contract, Core Scientific delivered 16 MW of HPC hosting capacity at its new Austin data center more than 30 days ahead of schedule.

Source (primary)

core-scientific 8-K exhibit (corzcoreweavehpc.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-04)Live source ↗

Quote: “In March of 2024, Core Scientific and CoreWeave entered a contract for HPC hosting at Core Scientific’s new Austin data center, with Core Scientific delivering 16 MW of capacity more than 30 days ahead of schedule.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (corzcoreweavehpc.htm)

Quote: “In March of 2024, Core Scientific and CoreWeave entered a contract for HPC hosting at Core Scientific’s new Austin data center, with Core Scientific delivering 16 MW of capacity more than 30 days ahead of schedule.”

View cached copy (2026-11-04)Live source ↗