NC-2/NC-3 initial utility capacity

Company: WhiteFiber

Subject kind
facility capacity
Statement date
2026-11-02
Promised amount
60.0 MW
Current status
stated

The claim, verbatim

The NC-2 and NC-3 properties are expected to provide a combined minimum of 60 MW of initial gross utility capacity.

Source (primary)

whitefiber 8-K exhibit (ea031063901ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-04)Live source ↗

Quote: “The properties are expected to provide a combined minimum of 60 megawatts (“MW”) of initial gross utility capacity”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms whitefiber 8-K exhibit (ea031063901ex99-1.htm)

Quote: “The properties are expected to provide a combined minimum of 60 megawatts (“MW”) of initial gross utility capacity”