CoreWeave 200 MW HPC operational 1H 2025
Company: Core Scientific
What the later record shows
Outcome not yet confirmed
The passages only repeat the expectation that the 200 MW would become operational in 1H 2025. A 2026 court filing says CoreWeave installed equipment at Denton, but no passage ties that to the 200 MW or says the 200 MW became operational.
“The site modifications commenced in the second half of fiscal 2024 and operational status is expected to begin in the first half of fiscal 2025.”
2026-03-01 · Core Scientific 10-K/A filed 2026-03-02 View cached copy (2026-08-31)Live source ↗
“As part of that deal, Core contends, “CoreWeave has installed HPC devices and equipment” in Core’s “Denton, Texas data center.””
2026-05-20 · In re: Core Scientific, Inc. — Entry #17: RESPONSE of Respondent Malikie Innovations Ltd View cached copy (2026-10-08)Live source ↗
Checked November 3, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The 200 MW of HPC infrastructure for CoreWeave (280 MW total) is expected to be operational in the first half of 2025.
Source (primary)
core-scientific 8-K exhibit (corescientificinvestorda.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-03)Live source ↗
Quote: “200 MW HPC infrastructure (280 MW total) ... Operational in 1H 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (corescientificinvestorda.htm)
Quote: “200 MW HPC infrastructure (280 MW total) ... Operational in 1H 2025”