2024 owned operational infrastructure target
Company: Core Scientific
What the later record shows
Partly delivered · happened December 31, 2024
The company reported about 784 MW of operational capacity as of December 31, 2024, which is short of the 796 MW target. The passage also does not say whether all of that capacity was owned.
“As of December 31, 2024, we have secured approximately 1,317 MW of contracted power capacity”
2025-03-27 · Core Scientific DEF 14A filed 2025-03-28 View cached copy (2026-08-31)Live source ↗
“with operational capacity of approximately 784 MW to support of our existing and planned HPC operations as well as our existing digital asset mining operations”
2025-03-27 · Core Scientific DEF 14A filed 2025-03-28 View cached copy (2026-08-31)Live source ↗
Checked November 3, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Core Scientific targets 796 MW of owned operational infrastructure in 2024.
Source (primary)
core-scientific 8-K exhibit (corescientificinvestorda.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-03)Live source ↗
Quote: “2024 goals and targets ... megawatts of owned operational infrastructure 796”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (corescientificinvestorda.htm)
Quote: “2024 goals and targets ... megawatts of owned operational infrastructure 796”