jain.com

Corsicana miner deployment

Company: Riot

Subject kind
facility capacity
Statement date
2024-06-12
Promised by
2024-12-31
Promised amount
61440.0 units
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

No passage gives the number of miners deployed at Corsicana. The October 2024 miner counts cover the whole MicroBT order, not Corsicana specifically.

“Riot has received a total of 89,438 miners from this order to date”
2024-10-29 · riot 8-K exhibit (riot-20241030xex99d2.htm) View cached copy (2026-10-25)Live source ↗

Checked November 3, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Riot is deploying 61,440 miners at Corsicana by year-end 2024.

Source (primary)

riot 8-K exhibit (riot-20240613xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-03)Live source ↗

Quote: “Deploying 61,440 miners by year-end 2024”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms riot 8-K exhibit (riot-20240613xex99d1.htm)

Quote: “Deploying 61,440 miners by year-end 2024”

View cached copy (2026-11-03)Live source ↗

Record of changes

November 3, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 3, 2026 — outcome unconfirmed