jain.com

Austin data center delivered to CoreWeave 30+ days early

Company: Core Scientific

Subject kind
facility timeline
Statement date
2024-06-24
Current status
stated

The claim, verbatim

Core Scientific delivered its Austin data center to CoreWeave more than 30 days ahead of schedule.

Source (primary)

core-scientific 8-K exhibit (ex991-finalcorzhpcoptionre.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-02)Live source ↗

Quote: “our Austin data center, which we delivered to CoreWeave more than 30 days ahead of schedule”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (ex991-finalcorzhpcoptionre.htm)

Quote: “our Austin data center, which we delivered to CoreWeave more than 30 days ahead of schedule”

View cached copy (2026-11-02)Live source ↗