Ellendale blockchain transformer replacement

Company: Applied Digital

Subject kind
facility timeline
Statement date
2024-06-24
Current status
stated

The claim, verbatim

The Ellendale blockchain facility has suffered power outages and transformer issues since early 2024; the company is installing replacement transformers to bring power back online.

Source (primary)

applied-digital 8-K exhibit (investorpresentationfina.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-02)Live source ↗

Quote: “Ellendale location faced power outages & transformer issues starting in early 2024. Installing replacement transformers and bringing the power back online.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms applied-digital 8-K exhibit (investorpresentationfina.htm)

Quote: “Ellendale location faced power outages & transformer issues starting in early 2024. Installing replacement transformers and bringing the power back online.”

View cached copy (2026-11-02)Live source ↗