Commerce Drive 25 MW expansion

Company: Riot

This claim was marked delayed on November 1, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2024-07-22
Promised by
2024-11-30
Promised amount
25.0 MW
Current status
delayed

What the later record shows

The date slipped

Kentucky developed capacity was still 60 MW in early 2025. In July 2025 a Commerce expansion was still listed as planned capex, so it was not completed around November 2024.

“Kentucky Facilities 60 MW Developed Capacity 305 MW Potential Capacity V Maximizing Value of 2.0 GW of Power Capacity”
2025-02-23 · riot 8-K exhibit (riot-20250224xex99d2.htm) View cached copy (2026-10-19)Live source ↗
“Includes infrastructure capex for 32 MW expansion at Commerce and 30 MW expansion at Blue Steel, growing total Kentucky power capacity from 65 MW to 127 MW”
2025-07-30 · riot 8-K exhibit (riot-20250731xex99d2.htm) View cached copy (2026-10-09)Live source ↗

Checked November 1, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

A 25 MW expansion at Commerce Drive, within the existing 60 MW PPA, is to be completed around November 2024.

Source (primary)

riot 8-K exhibit (riot-20240723xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗

Quote: “25MW expansion at Commerce completed in ~Nov 2024. Expansion by 25MW is within the existing 60MW PPA.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms riot 8-K exhibit (riot-20240723xex99d2.htm)

Quote: “25MW expansion at Commerce completed in ~Nov 2024. Expansion by 25MW is within the existing 60MW PPA.”

View cached copy (2026-11-01)Live source ↗

delays riot 8-K exhibit (riot-20250731xex99d2.htm)

Quote: “Includes infrastructure capex for 32 MW expansion at Commerce and 30 MW expansion at Blue Steel, growing total Kentucky power capacity from 65 MW to 127 MW”

View cached copy (2026-10-09)Live source ↗

delays riot 8-K exhibit (riot-20250224xex99d2.htm)

Quote: “Kentucky Facilities 60 MW Developed Capacity 305 MW Potential Capacity V Maximizing Value of 2.0 GW of Power Capacity”

View cached copy (2026-10-19)Live source ↗

Record of changes

November 1, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
November 1, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.