Block Mining sites to 110 MW by end-2024
Company: Riot
What the later record shows
The date slipped
Kentucky developed capacity was still 60 MW in early 2025, well short of the 110 MW targeted for the end of 2024. Later Kentucky totals (192 MW at YE2025) are not broken out by site, so they cannot be attributed to Block Mining's two original sites.
“Kentucky Facilities 60 MW Developed Capacity 305 MW Potential Capacity”
2025-02-23 · riot 8-K exhibit (riot-20250224xex99d2.htm) View cached copy (2026-10-19)Live source ↗
“Kentucky Facility 192 60 Total power capacity 1,292 1,160”
2026-03-01 · Riot 10-K filed 2026-03-02 View cached copy (2026-08-31)Live source ↗
Checked November 1, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Riot intends to expand Block Mining's two sites, targeting 110 MW for self-mining by the end of 2024, under existing agreements.
Source (primary)
riot 8-K exhibit (riot-20240723xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗
Quote: “Riot intends to further expand Block Mining ’ s two sites, targeting 110 MW for self-mining operations by the end of 2024.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms riot 8-K exhibit (riot-20240723xex99d1.htm)
Quote: “Riot intends to further expand Block Mining ’ s two sites, targeting 110 MW for self-mining operations by the end of 2024.”
delays Riot 10-K filed 2026-03-02
Quote: “Kentucky Facility 192 60 Total power capacity 1,292 1,160”
delays riot 8-K exhibit (riot-20250224xex99d2.htm)
Quote: “Kentucky Facilities 60 MW Developed Capacity 305 MW Potential Capacity”