Corsicana initial phase adds 16 EH/s by end-2024
Company: Riot
What the later record shows
Partly delivered
Corsicana's deployed hash rate was 14.1 EH/s at year-end 2024 and 15.7 EH/s at year-end 2025, short of the 16 EH/s promised. Riot cited a pivot to AI/HPC at Corsicana as reducing hash rate growth.
“Pivot to AI/HPC at Corsicana reduced 2025 hash rate growth by 8 EH/s”
2025-02-23 · riot 8-K exhibit (riot-20250224xex99d2.htm) View cached copy (2026-10-19)Live source ↗
“Rockdale Facility 15.0 12.4 9.7 Corsicana Facility 14.1 — — Kentucky Facility 2.4”
2025-02-27 · Riot 10-K filed 2025-02-28 View cached copy (2026-08-31)Live source ↗
“Rockdale Facility 16.4 15.0 Corsicana Facility 15.7 14.1 Kentucky Facility 6.4”
2026-03-01 · Riot 10-K filed 2026-03-02 View cached copy (2026-08-31)Live source ↗
Checked November 1, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The initial 400 MW phase of the Corsicana Facility is expected to add 16 EH/s of self-mining capacity by the end of 2024.
Source (primary)
riot 8-K exhibit (riot-20240731xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗
Quote: “This initial phase is expected to add 16 EH/s to Riot’s self-mining capacity by the end of 2024.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms riot 8-K exhibit (riot-20240731xex99d1.htm)
Quote: “This initial phase is expected to add 16 EH/s to Riot’s self-mining capacity by the end of 2024.”