Corsicana remaining two buildings (first 400 MW phase) operational
Company: Riot
What the later record shows
Delivered on time · happened December 31, 2024
The 2024 10-K states that Phase I of the Corsicana Facility (400 MW) was completed during 2024, and it shows 400 MW of developed capacity at December 31, 2024.
“During 2024, we completed Phase I of development of the Corsicana Facility, a second large-scale Bitcoin mining facility, currently equipped to provide up to 400 megawatts”
2025-02-27 · Riot 10-K filed 2025-02-28 View cached copy (2026-08-31)Live source ↗
“Construction of this first phase was completed during the year ended December 31, 2024.”
2025-12-30 · Riot 424B5 filed 2025-12-31 View cached copy (2026-08-31)Live source ↗
Checked November 1, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Riot expects the remaining two buildings at its Corsicana Facility, completing the first 400 MW phase, to be fully operational by the end of 2024.
Source (primary)
riot 8-K exhibit (riot-20240731xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-11-01)Live source ↗
Quote: “The remaining two buildings representing the completion of the first 400 MW at our Corsicana Facility are expected to be fully operational by the end of 2024.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms riot 8-K exhibit (riot-20240731xex99d1.htm)
Quote: “The remaining two buildings representing the completion of the first 400 MW at our Corsicana Facility are expected to be fully operational by the end of 2024.”
confirms Riot 10-K filed 2025-02-28
Quote: “During 2024, we completed Phase I of development of the Corsicana Facility, a second large-scale Bitcoin mining facility, currently equipped to provide up to 400 megawatts”
confirms Riot 424B5 filed 2025-12-31
Quote: “Construction of this first phase was completed during the year ended December 31, 2024.”