2024 target: 16 MW operational HPC infrastructure
Company: Core Scientific
What the later record shows
Delivered on time · happened March 31, 2024
The company states it delivered 16 MW of billable HPC capacity to CoreWeave at Austin in March 2024, well before the year-end target.
“March: Delivered 16 MW of billable capacity to CoreWeave >30 days ahead of schedule”
2025-05-06 · core-scientific 8-K exhibit (exhibit992-q12025earning.htm) View cached copy (2026-10-16)Live source ↗
Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The company's 2024 target is 16 MW of operational HPC infrastructure.
Source (primary)
core-scientific 8-K exhibit (corescientificq22024earn.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗
Quote: “MW operational HPC infrastructure 16”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (corescientificq22024earn.htm)
Quote: “MW operational HPC infrastructure 16”
confirms core-scientific 8-K exhibit (exhibit992-q12025earning.htm)
Quote: “March: Delivered 16 MW of billable capacity to CoreWeave >30 days ahead of schedule”