Full 382 MW HPC delivery by H1 2026
Company: Core Scientific
What the later record shows
Outcome not yet confirmed
The Q2 2026 10-Q says colocation is still ramping toward full operational capacity, but it does not say how much of the 382 MW across the five ASDCs was delivered. An October 2026 headline about 485 MW of billing capacity is not tied to this scope in the passage text, so neither full nor partial delivery can be confirmed.
“the associated operating cash flows generated as our colocation business ramps towards full operational capacity also contributed to the overall improvement in operating cash flows.”
2026-07-27 · Core Scientific 10-Q filed 2026-07-28 View cached copy (2026-08-30)Live source ↗
Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The estimated delivery timeline for 382 MW of HPC application-specific data center infrastructure covers five ASDCs, with deliveries running from H2 2024 through H1 2026.
Source (primary)
core-scientific 8-K exhibit (corescientificq22024earn.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗
Quote: “382 MW HPC application-specific data center (ASDC) infrastructure estimated delivery timeline H2 2024 ... H1 2026”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (corescientificq22024earn.htm)
Quote: “382 MW HPC application-specific data center (ASDC) infrastructure estimated delivery timeline H2 2024 ... H1 2026”