First CoreWeave HPC MW energized in 1H 2025
Company: Core Scientific
What the later record shows
Delivered on time
The May 6, 2025 materials show MW already delivered at Denton, a CoreWeave site, with more expected that month. That places first energization before the 1H 2025 deadline. The chart text is garbled, so the exact date and MW are uncertain.
“Q4Q3Q2Q1 ~17 MW delivered Austin, TX ~65 MW delivered + ~40 MW Denton ~25 MW delivered + 8 MW Denton”
2025-05-06 · core-scientific 8-K exhibit (exhibit992-q12025earning.htm) View cached copy (2026-10-16)Live source ↗
“Expect to deliver 8 MW of billable capacity at Denton this month and an additional 40 MW by the end of the second quarter”
2025-05-06 · core-scientific 8-K exhibit (exhibit992-q12025earning.htm) View cached copy (2026-10-16)Live source ↗
Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The company expects HPC megawatts under the CoreWeave contracts to be energized in the first half of 2025.
Source (primary)
core-scientific 8-K exhibit (corescientificq22024earn.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗
Quote: “HPC MW energized in 1H of 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (corescientificq22024earn.htm)
Quote: “HPC MW energized in 1H of 2025”
confirms core-scientific 8-K exhibit (exhibit992-q12025earning.htm)
Quote: “Q4Q3Q2Q1 ~17 MW delivered Austin, TX ~65 MW delivered + ~40 MW Denton ~25 MW delivered + 8 MW Denton”