Ellendale HPC LOI exclusivity extended
Company: Applied Digital
The claim, verbatim
On July 26, 2024 the company agreed to extend the exclusivity period under the LOI for leasing its Ellendale, North Dakota HPC data center campus.
Source (primary)
applied-digital 8-K exhibit (apldq424earningsrelease.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-30)Live source ↗
Quote: “On July 26, 2024, Applied Digital Corporation entered into an agreement extending the exclusivity period under the previously announced LOI for leasing the Company's Ellendale, North Dakota HPC data center campus.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms applied-digital 8-K exhibit (apldq424earningsrelease.htm)
Quote: “On July 26, 2024, Applied Digital Corporation entered into an agreement extending the exclusivity period under the previously announced LOI for leasing the Company's Ellendale, North Dakota HPC data center campus.”