jain.com

AMD leases 377 MW critical IT capacity across Pecos, Muskogee, Hunt County

Company: Core Scientific

Subject kind
customer
Statement date
2026-07-28
Promised amount
377.0 MW
Current status
stated

The claim, verbatim

Core Scientific already leases 377 MW of critical IT capacity to AMD across its Pecos, Muskogee and Hunt County campuses, per its July 28 8-K (Item 7.01).

Source (primary)

KBW sees Anthropic’s AMD and overseas lease plans favoring Core Scientific and TeraWulf, backstops still required - Yahoo Finance (-, news_article)
View cached copy (2026-10-28)Live source ↗

Quote: “Core Scientific already leases 377 MW of critical IT capacity to AMD across Pecos, Muskogee and Hunt County, according to its July 28 8-K under Item 7.01”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms KBW sees Anthropic’s AMD and overseas lease plans favoring Core Scientific and TeraWulf, backstops still required - Yahoo Finance

Quote: “Core Scientific already leases 377 MW of critical IT capacity to AMD across Pecos, Muskogee and Hunt County, according to its July 28 8-K under Item 7.01”

View cached copy (2026-10-28)Live source ↗