HPC liquid-cooled infrastructure delivery starting 1H 2025

Company: Core Scientific

Subject kind
facility timeline
Statement date
2024-10-06
Promised by
2025-06-30
Current status
verified

What the later record shows

Delivered on time · happened March 31, 2025

The Q1 2025 earnings deck (published 2025-05-06) shows ~17 MW already delivered at Austin, TX for CoreWeave in Q1, so delivery to the HPC customer began within 1H 2025. A later deck says the company energized substantial capacity in 2025. Confidence is medium because the deck text is a garbled chart and no passage explicitly mentions liquid cooling.

“Q4Q3Q2Q1 ~17 MW delivered Austin, TX ~65 MW delivered + ~40 MW Denton ~25 MW delivered + 8 MW Denton”
2025-05-06 · core-scientific 8-K exhibit (exhibit992-q12025earning.htm) View cached copy (2026-10-16)Live source ↗
“Energized as many MWs as the rest of publicly traded peers combined in 2025”
2026-05-05 · core-scientific 8-K exhibit (q1fy26earningsdeck.htm) View cached copy (2026-09-08)Live source ↗

Checked October 26, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

The company committed to begin delivering powered infrastructure with advanced liquid cooling, optimized for AI GPU cloud workloads, to its HPC customer in the first half of 2025.

Source (primary)

core-scientific 8-K exhibit (corescientificseptember202.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-26)Live source ↗

Quote: “We remain committed to delivering powered infrastructure equipped with advanced liquid cooling systems, specifically optimized for AI GPU cloud workloads, for our HPC customer beginning in the first half of 2025.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms core-scientific 8-K exhibit (corescientificseptember202.htm)

Quote: “We remain committed to delivering powered infrastructure equipped with advanced liquid cooling systems, specifically optimized for AI GPU cloud workloads, for our HPC customer beginning in the first half of 2025.”

View cached copy (2026-10-26)Live source ↗

confirms core-scientific 8-K exhibit (q1fy26earningsdeck.htm)

Quote: “Energized as many MWs as the rest of publicly traded peers combined in 2025”

View cached copy (2026-09-08)Live source ↗

confirms core-scientific 8-K exhibit (exhibit992-q12025earning.htm)

Quote: “Q4Q3Q2Q1 ~17 MW delivered Austin, TX ~65 MW delivered + ~40 MW Denton ~25 MW delivered + 8 MW Denton”

View cached copy (2026-10-16)Live source ↗

Record of changes

October 26, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 26, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.