Remaining MicroBT miner deliveries
Company: Riot
What the later record shows
The date slipped · new target June 30, 2025
The 10-K filed after year-end 2024 says the MicroBT miners are now expected to be received and deployed by mid-2025, not by the end of 2024. Later filings push receipt of all ordered miners to Q2 2026.
“Delivery of the MicroBT miners initially began in the fourth quarter of 2023 and will be completed in monthly batches according to the delivery schedules specified under the applicable purchase order. All miners are expected to be received and deployed by mid-2025.”
2025-02-27 · Riot 10-K filed 2025-02-28 View cached copy (2026-08-31)Live source ↗
“all miners under these purchase orders are expected to be received by the second quarter of 2026, with deployment following on an ongoing basis”
2025-10-29 · Riot 10-Q filed 2025-10-30 View cached copy (2026-08-31)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The remaining 41,902 miners from the MicroBT purchase order are to be received and deployed through the end of 2024.
Source (primary)
riot 8-K exhibit (riot-20241030xex99d2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “the remaining balance of 41,902 miners to be received and deployed through the end of 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms riot 8-K exhibit (riot-20241030xex99d2.htm)
Quote: “the remaining balance of 41,902 miners to be received and deployed through the end of 2024”
delays Riot 10-K filed 2025-02-28
Quote: “Delivery of the MicroBT miners initially began in the fourth quarter of 2023 and will be completed in monthly batches according to the delivery schedules specified under the applicable purchase order. All miners are expected to be received and deployed by mid-2025.”
delays Riot 10-Q filed 2025-10-30
Quote: “all miners under these purchase orders are expected to be received by the second quarter of 2026, with deployment following on an ongoing basis”