Corsicana: two new buildings online in 2025

Company: Riot

This claim was marked delayed on October 25, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2024-10-29
Promised by
2025-12-31
Promised amount
2.0 units
Current status
delayed

What the later record shows

The date slipped

Corsicana's developed capacity was 400 MW at year-end 2024 and was still 400 MW at year-end 2025. That 400 MW is the Phase I buildout completed in 2024, so the two additional buildings promised for 2025 do not show up. In October 2025 Riot instead described new Corsicana buildings as data-center Core & Shell, with construction starting in Q1 2026.

“As part of Corsicana Phase 1, Riot has initiated Core & Shell development of two buildings, each consisting of 56 MW of critical IT load capacity”
2025-10-29 · riot 8-K exhibit (riot-20251030xex99d2.htm) View cached copy (2026-09-27)Live source ↗
“The first phase of the development of the Corsicana Facility involved the construction of 400 MW of immersion-cooled Bitcoin Mining infrastructure”
2025-12-30 · Riot 424B5 filed 2025-12-31 View cached copy (2026-08-31)Live source ↗
“Rockdale Facility ​ ​ 700 ​ ​ 700 Corsicana Facility ​ ​ 400 ​ ​ 400 Kentucky Facility ​ ​ 192 ​ ​ 60”
2026-03-01 · Riot 10-K filed 2026-03-02 View cached copy (2026-08-31)Live source ↗

Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Lead times for the next Corsicana substation are longer than expected. As a result, two new buildings will come online at the Corsicana Facility in 2025, instead of the three previously expected.

Source (primary)

riot 8-K exhibit (riot-20241030xex99d1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗

Quote: “longer than anticipated lead times for the next substation at the Corsicana Facility, which will result in two new buildings coming online in 2025 versus prior expectations for three buildings”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms riot 8-K exhibit (riot-20241030xex99d1.htm)

Quote: “longer than anticipated lead times for the next substation at the Corsicana Facility, which will result in two new buildings coming online in 2025 versus prior expectations for three buildings”

View cached copy (2026-10-25)Live source ↗

delays Riot 424B5 filed 2025-12-31

Quote: “The first phase of the development of the Corsicana Facility involved the construction of 400 MW of immersion-cooled Bitcoin Mining infrastructure”

View cached copy (2026-08-31)Live source ↗

delays Riot 10-K filed 2026-03-02

Quote: “Rockdale Facility ​ ​ 700 ​ ​ 700 Corsicana Facility ​ ​ 400 ​ ​ 400 Kentucky Facility ​ ​ 192 ​ ​ 60”

View cached copy (2026-08-31)Live source ↗

delays riot 8-K exhibit (riot-20251030xex99d2.htm)

Quote: “As part of Corsicana Phase 1, Riot has initiated Core & Shell development of two buildings, each consisting of 56 MW of critical IT load capacity”

View cached copy (2026-09-27)Live source ↗

Record of changes

October 25, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 25, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.