jain.com

Ellendale 100 MW HPC data center construction

Company: Applied Digital

Subject kind
facility capacity
Statement date
2024-11-04
Promised amount
400.0 MW
Current status
stated

The claim, verbatim

Applied Digital has begun building a 100 MW HPC data center in Ellendale, North Dakota, next to its existing 180 MW hosting facility. It is the first of three planned buildings on the site, which are meant to total 400 MW.

Source (primary)

applied-digital 8-K exhibit (ex99-2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗

Quote: “We also began construction of a 100 MW HPC data center in Ellendale, North Dakota, on land located adjacent to our existing 180 MW Data center hosting facility, which is the first of three planned buildings on this site for a total of 400 MW of capacity.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms applied-digital 8-K exhibit (ex99-2.htm)

Quote: “We also began construction of a 100 MW HPC data center in Ellendale, North Dakota, on land located adjacent to our existing 180 MW Data center hosting facility, which is the first of three planned buildings on this site for a total of 400 MW of capacity.”

View cached copy (2026-10-25)Live source ↗