CoreWeave delivery: 270 MW by 2H 2025
Company: Core Scientific
What the later record shows
The date slipped
The October 2025 timeline targets only 250 MW cumulative by the end of 2025, below the 270 MW promised for 2H 2025. The full 590 MW now comes by early 2027, and no specific new date for 270 MW is given.
“On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”
2025-10-30 · Investor Conference Call Presentation View cached copy (2026-09-26)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The company targets cumulative delivery of 270 MW of HPC infrastructure to CoreWeave by the end of 2H 2025.
Source (primary)
core-scientific 8-K exhibit (corescientificq32024earn.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “1H 2025 2H 2025 1H 2026 2H 2026 200MW 270MW 382MW 500MW Cumulative infrastructure delivery timeline”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (corescientificq32024earn.htm)
Quote: “1H 2025 2H 2025 1H 2026 2H 2026 200MW 270MW 382MW 500MW Cumulative infrastructure delivery timeline”
delays Investor Conference Call Presentation
Quote: “On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”