CoreWeave delivery: 200 MW by 1H 2025
Company: Core Scientific
What the later record shows
The date slipped · new target December 31, 2025
In late October 2025, well after the 1H 2025 deadline, the company reported only ~120+ MW energized at Denton and Marble. It said it was on track for 250 MW by the end of 2025, so 200 MW was not reached by June 30, 2025.
“~120+ MW Energized Across Denton & Marble Sites Contracted site construction progress”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗
“On track to energize 250 MW by the end of 2025 and a total of 590 MW by early 2027”
2025-10-29 · core-scientific 8-K exhibit (ef20057996_ex99-1.htm) View cached copy (2026-09-27)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The company targets cumulative delivery of 200 MW of HPC infrastructure to CoreWeave by the end of 1H 2025.
Source (primary)
core-scientific 8-K exhibit (corescientificq32024earn.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “1H 2025 2H 2025 1H 2026 2H 2026 200MW 270MW 382MW 500MW Cumulative infrastructure delivery timeline”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms core-scientific 8-K exhibit (corescientificq32024earn.htm)
Quote: “1H 2025 2H 2025 1H 2026 2H 2026 200MW 270MW 382MW 500MW Cumulative infrastructure delivery timeline”
delays core-scientific 8-K exhibit (ef20057996_ex99-1.htm)
Quote: “~120+ MW Energized Across Denton & Marble Sites Contracted site construction progress”