August 2024 Bitmain S21 XP agreement remaining balance
Company: IREN
What the later record shows
Outcome not yet confirmed
Later filings restate the $45.3 million balance as due, first in June and July 2025 and then by July 2025. No passage confirms it was actually paid.
“As of December 31, 2024, we have paid $181.1 million relating to the August 2024 Agreement, and the remaining balance is due in June and July 2025.”
2025-03-19 · iren 8-K exhibit (irenlimited-exx992dec2024x.htm) View cached copy (2026-10-18)Live source ↗
“the remaining balance of $45.3 million for the purchase of such 39,000 miners is due by July 2025”
2025-05-13 · iren 8-K exhibit (irenlimited-exx994mar2025.htm) View cached copy (2026-10-15)Live source ↗
Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The remaining balance of about $45.3 million for 39,000 S21 XP miners under the August 2024 Bitmain agreement is due in July and August 2025.
Source (primary)
iren 8-K exhibit (irisenergylimited-exx994se.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗
Quote: “As of September 30, 2024, we have paid $181.1 million relating to the August 2024 Agreement, and the remaining balance is due in July and August 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irisenergylimited-exx994se.htm)
Quote: “As of September 30, 2024, we have paid $181.1 million relating to the August 2024 Agreement, and the remaining balance is due in July and August 2025”