810MW data center capacity by H1 2025

Company: IREN

Subject kind
facility capacity
Statement date
2024-12-05
Promised by
2025-06-30
Promised amount
810.0 MW
Current status
verified

What the later record shows

Delivered; the record does not say when

The update dated 2025-07-06 shows 810MW operating, up from 510MW at end-2024. It does not say whether this was reached by 30 June 2025.

“Canada Grid-Connected Power Secured USA 810MW Operating 2,100MW Under Construction / Power secured”
2025-07-06 · iren 8-K exhibit (ef20051646_ex99-1.htm) View cached copy (2026-10-11)Live source ↗

Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN accelerated its target of 810MW of data center capacity to H1 2025.

Source (primary)

iren 8-K exhibit (nov2024monthlyupdatevdc.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗

Quote: “810MW accelerated to H1 2025”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)

Quote: “810MW accelerated to H1 2025”

View cached copy (2026-10-24)Live source ↗

confirms iren 8-K exhibit (ef20051646_ex99-1.htm)

Quote: “Canada Grid-Connected Power Secured USA 810MW Operating 2,100MW Under Construction / Power secured”

View cached copy (2026-10-11)Live source ↗

Record of changes

October 24, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 24, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.