810MW data center capacity by H1 2025
Company: IREN
What the later record shows
Delivered; the record does not say when
The update dated 2025-07-06 shows 810MW operating, up from 510MW at end-2024. It does not say whether this was reached by 30 June 2025.
“Canada Grid-Connected Power Secured USA 810MW Operating 2,100MW Under Construction / Power secured”
2025-07-06 · iren 8-K exhibit (ef20051646_ex99-1.htm) View cached copy (2026-10-11)Live source ↗
Checked October 24, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN accelerated its target of 810MW of data center capacity to H1 2025.
Source (primary)
iren 8-K exhibit (nov2024monthlyupdatevdc.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-24)Live source ↗
Quote: “810MW accelerated to H1 2025”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)
Quote: “810MW accelerated to H1 2025”
confirms iren 8-K exhibit (ef20051646_ex99-1.htm)
Quote: “Canada Grid-Connected Power Secured USA 810MW Operating 2,100MW Under Construction / Power secured”