$6-8M per MW build cost beyond CB2
Company: TeraWulf
The claim, verbatim
TeraWulf is confident it can deliver buildings beyond CB2 at $6M to $8M per MW, provided it returns to market to lock in pricing within the next three to four months.
Source (primary)
terawulf 8-K exhibit (eh240572111_ex9901.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-22)Live source ↗
Quote: “we're pretty confident that being able to deliver on that $6 million to $8 million per megawatt for buildings beyond CB2 is possible”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (eh240572111_ex9901.htm)
Quote: “we're pretty confident that being able to deliver on that $6 million to $8 million per megawatt for buildings beyond CB2 is possible”