Miner building 5 (MB-5) completion

Company: TeraWulf

Subject kind
facility timeline
Statement date
2025-01-02
Promised by
2025-02-15
Promised amount
50.0 MW
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

No passage mentions miner building 5 (MB-5) or when it was completed. The 10-Q references to energized bitcoin capacity across 'three buildings' are not tied to MB-5.

Checked October 22, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Construction of miner building 5 (50 MW) is on schedule, with foundation pours completed and framing underway. Completion is targeted for mid Q1 2025.

Source (primary)

terawulf 8-K exhibit (wulfopsreport-202412dec2.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-22)Live source ↗

Quote: “Construction of miner building 5 (MB-5, 50 MW) is proceeding on schedule, with foundation pours completed and building framing underway, with target completion in mid Q1 2025.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulfopsreport-202412dec2.htm)

Quote: “Construction of miner building 5 (MB-5, 50 MW) is proceeding on schedule, with foundation pours completed and building framing underway, with target completion in mid Q1 2025.”

View cached copy (2026-10-22)Live source ↗

Record of changes

October 22, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 22, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.