50 EH/s hashrate target
Company: IREN
What the later record shows
Delivered on time · happened June 29, 2025
IREN announced the 50 EH/s milestone on June 29, 2025, before the five-month deadline of about July 5, 2025.
“With 50 EH/s of mining expansion complete, we’re now turning to our next frontier”
2025-06-29 · iren 8-K exhibit (a50ehsupdate_vff.htm) View cached copy (2026-10-11)Live source ↗
Checked October 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN said it is on track to reach 50 EH/s of installed hashrate within 5 months.
Source (primary)
iren 8-K exhibit (janmonthlyupdatevff.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-20)Live source ↗
Quote: “On-track for 50 EH/s in 5 months”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (janmonthlyupdatevff.htm)
Quote: “On-track for 50 EH/s in 5 months”
confirms iren 8-K exhibit (a50ehsupdate_vff.htm)
Quote: “With 50 EH/s of mining expansion complete, we’re now turning to our next frontier”