Grid-connected capacity in 2025

Company: IREN

Subject kind
facility capacity
Statement date
2025-02-11
Promised by
2025-12-31
Promised amount
910.0 MW
Current status
outcome unconfirmed

What the later record shows

Partly delivered

Operating capacity rose to 810MW by June 30, 2025. The remaining capacity (Horizon 1, 75MW) was still under construction, and no passage shows 910MW reached in 2025.

“Childress BTC Mining (Texas, USA) 650 40.1 Operating Total Operating 810 50.0 Childress Horizon 1 (Texas, USA) 75 N/A Under construction”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗

Checked October 20, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN has 510MW of grid connection, rising to 910MW in 2025.

Source (primary)

iren 8-K exhibit (q2fy25resultspresentatio.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-20)Live source ↗

Quote: “510MW (910MW in 2025)”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (q2fy25resultspresentatio.htm)

Quote: “510MW (910MW in 2025)”

View cached copy (2026-10-20)Live source ↗

Record of changes

October 20, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 20, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.