Stingray data center site acquisition
Company: Cipher Mining
The claim, verbatim
Cipher closed the acquisition of the Stingray data center site in West Texas. The site has 100 MW of front-of-the-meter capacity, all necessary regulatory approvals and 250 acres of land adjacent to transmission assets.
Source (primary)
cipher-mining 8-K exhibit (cifr-20250225xex991.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-19)Live source ↗
Quote: “Completed acquisition of Stingray data center site, featuring 100 MW of front-of-the-meter capacity, all necessary regulatory approvals, and 250 acres of land adjacent to transmission assets”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms cipher-mining 8-K exhibit (cifr-20250225xex991.htm)
Quote: “Completed acquisition of Stingray data center site, featuring 100 MW of front-of-the-meter capacity, all necessary regulatory approvals, and 250 acres of land adjacent to transmission assets”