jain.com

30,050 Bitmain S21 Pro miners, final payment by July 2025

Company: IREN

Subject kind
acquisition
Statement date
2025-03-19
Promised by
2025-07-31
Promised amount
132900000.0 USD
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

Later filings describe the January 2025 option exercise with different miner counts (48,030 S21 Pro plus 30,000 S21 XP) and say only that the majority were delivered by June 30, 2025. A balance on the exercised miners was still due by October 2025; no passage confirms the final payment by July 2025.

“$119.3 million for the purchase of the additional 47,980 miners is due by October 2025”
2025-05-13 · iren 8-K exhibit (irenlimited-exx994mar2025.htm) View cached copy (2026-10-15)Live source ↗
“The majority of miners have been delivered as of June 30, 2025.”
2025-08-27 · IREN 10-K filed 2025-08-28 View cached copy (2026-08-31)Live source ↗

Checked October 18, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

On January 2, 2025 IREN exercised options for the remaining 30,050 Bitmain S21 Pro miners (7.0 EH/s) for $132.9 million, with the final payment due by July 2025.

Source (primary)

iren 8-K exhibit (irenlimited-exx992dec2024x.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-18)Live source ↗

Quote: “On January 2, 2025, we exercised options for the remaining 30,050 S21 Pro miners, with a total hashrate of 7.0 EH/s for $18.9/TH and a total purchase price of $132.9 million, with the final payment due by July 2025.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (irenlimited-exx992dec2024x.htm)

Quote: “On January 2, 2025, we exercised options for the remaining 30,050 S21 Pro miners, with a total hashrate of 7.0 EH/s for $18.9/TH and a total purchase price of $132.9 million, with the final payment due by July 2025.”

View cached copy (2026-10-18)Live source ↗

Record of changes

October 18, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 18, 2026 — outcome unconfirmed